Thursday, April 30, 2009

Week of April 27, 2009

The construction site now has a new sign. It is official we are building the new school.
Foundations and footings are 3/4 completed. This is the gym and cafe side of the new building project.

Construction workers are back filling the foundations and putting in outside lighting poles.
First layer of asphalt installed for the parking lots and driveways.
The dirt mountains are beginning to be moved around the new site.





Wednesday, April 15, 2009

Foundation and roadwork

This week the construction site is very active at moving the top soil around the building site.

More pile of top soil being moved to areas around the site to be spread at a later date.

Roadwork and preparing the driveway and parking lots of the new site.

The foundation is being poured at the front of the building. The footings are being prepared for the walls to be set and poured. In the distance you can see the entrance to the third and fourth grade wing.






Wednesday, April 8, 2009

Underground piping and the (blue) foundation being installed.
Installing the foundations on the k-2 wing and the 3-4 wing with blue insulation.


Underground piping for the lighting in the parking lot.

Finishing the driveway off from Hallowell Road.

Leveling the parking lot and installing the cement lighting foundation.



Bus Circle


Contractors are working on the bus circle that will be located in the front of the new building.