Thursday, March 19, 2009

Construction of the entrance to the new school began this week.

Drainage and roadwork continues this week.
More drainage and water run-off collection drains being installed.

Dirt piles continue to grow as the site becomes level to begin building.
Leveling the site and building the roads.
March 14 and 15th the new septic system was connected to the old building until the new building is completed. The school was closed for the weekend until the septic system was back on line. Progress on the site is moving fast and it is amazing to see how quickly the construction workers move the material around the site.

Monday, March 9, 2009

March 9, 2009 Construction UpDate

Septic Tank and Leach Field are completed and scheduled to be connected to the old school on March 14, 2009. The old septic system needs to be removed for the new foundation of the new building to be prepared,
Dirt mount behind the portable classrooms of grades 3-5.

The dirt mount on the old baseball field at third base.

Dirt mound behind the portable classrooms of grades 3-5.






Friday, March 6, 2009

Site Prep Mountains of Dirt


Construction company is clearing the top soil to prep the site for development. The soil piles will be come larger.

Building the Road to the New School Site